How it started vs How it’s going… 1 year later
Since breaking ground in September 2023, Muhammad Azeem’s team have achieved near-completion of the 132kV / 22kV Substation in Kemps Creek in Western Sydney.
With the unwavering support of our incredible delivery partners such as Avant Constructions, Field Energy Services and Ampcontrol, the project remains on schedule and is now very close to completion.
Latest project milestones:
Installation of all primary electrical protection equipment
Installation of all busbar configurations
Installation of all overhead conductors
Completion of all fibre and protection wiring configurations
Completion of the Substation Earth Grid connections
Installation of all primary and secondary cables
Testing is underway, in preparation for commissioning when our client is ready to energise their substation, which will power important infrastructure being built to support communities and businesses.
Enjoy these progress shots as we near final completion, and if you’d like to discuss how Ausconnex can support you with Engineering, Procurement, Construction, Maintenance and Operation of High Voltage Substations, please reach out via our Contact page.